Guangzhou Clearance Case: Used Press Moulding Machine from Taiwan
Seahog has been regularly handling the import clearance of used machines and second-hand equipment. Here comes a recent case. Seahog Guangzhou team helped clear one used press moulding machine for PCB industry via Nansha port Guangzhou. This used machine, originated in Japan was shipped from Taiwan, China. Before shipping the pre-shipment inspection was executed and the certificate was obtained, and all paperwork was well prepared, so the declarations were immediately made when the customs manifest was available. The whole process was all handled quickly and smoothly, including the price verification and the inspection sections. The client was very happy with our services, as pictured are the relevant customs declaration sheet and a picture which was taken when the used machine was about to un-veiled for the inspection.


By this case, we would like to share the key points for China import clearance for used machines and second-hand equipment.
1 Locate the HS code and customs supervision conditions, therein the below three are most common
A refers to legal inspection, all used machines and second-hand equipment shall accept this supervision
O means that the subject machines/equipment shall obtain automatic import license
6 means that the subject machines/equipment are banned from importing into China.
2 check three aspects of the machine(s)
Year of manufacturing: machine(s) and equipment that are more than ten years old might be identified as solid waste by China customs.
Name plate: make sure that the nameplate indicates clear info
Original factory invoice and maintenance record are important documents for price verification
3. Pre-shipment inspection
The pre-shipment inspection is mainly to check the completeness of the appearance and structure and whether the machine(s) can work normally.
The naked electric wires shall be well wrapped
The greasy dirt shall be removed thoroughly
The warning signs shall be put on as regulated
Ship the used machines/second-hand equipment after they passes -pre-shipment inspection.
Used machines and second-hand equipment not accept or pass the pre-shipment inspection will end up being returned by China customs.
4 Required documents for clearance in China
1 basic documents include: contract, invoice, packing list, bill of lading
2 automatic import license is required for certain machines and equipment. For regular equipment, the license shall be obtained from Provincial Department of Commerce, while the license of key equipment shall be approved by Department of Commerce in Beijing.
3 pre-shipment inspection certificate
4. large-sized complete sets of equipment shall provide layout picture.
5. colored pictures of the machine/equipment,